Providing no further slips come down – the highway will remain open 24 hours a day from now, under regular supervision.

SH25 has also opened up to two lanes on the other side of the Peninsula between Hikuai and Opoutere this afternoon, following pavement stabilisation and the installation of temporary ramps.

The highway has been greatly compromised by a major under-slip at Opoutere since 6 March. Contractors cut into the bank to create a temporary lane before completing a permanent retaining wall.

On the Thames Coast highway, there has been issues with cliff stability for a fortnight since two large slips fell on Saturday 24 June.

“It’s been a huge job for our contractors, not only clearing the initial slips, but facing the on-going risk and challenge of slip material continuing to come down over the last two weeks,” says Waka Kotahi Journey Manager for the Waikato, Liam Ryan.

“The job has involved clearing hundreds of cubic metres of material away from site and efforts to mitigate the risk of further slips with abseiling specialists removing loose rock, arborists bringing down dangerous trees and sluicing of the cliff face using water dumped by helicopter.

“The road has been fully closed multiple times for public safety and to enable the work to take place. Road users have put up with long delays until vehicles could be piloted through or the road was re-opened to one lane under stop/go.

“In all of the work around the Coromandel, the priority for Waka Kotahi contractors has been clearing a pathway for emergency services then ensuring communities are reconnected as quickly and safely as possible,” Mr Ryan says.

The work done on all slip sites should improve ongoing resilience on this highway, but road users should expect wet weather will continue to pose a risk around the Peninsula.

Work will resume at SH25 Opoutere on Monday which will require periods of one hour long stop/stop closures. Asphalt surfacing is planned to take place on Tuesday night 11 July with up to one hour stop/stop closures required overnight from around 7pm.

“We appreciate how inconvenient these major repairs works have been for the communities, visitors and businesses on the Coromandel Peninsula – especially with the long-term closure of SH25A and thank everyone for their patience.”

Important information for drivers

Weather warning

  • The Metservice has issued a heavy rain watch for Nelson, west of Mapua, between 9 pm Friday and 9 pm Saturday. This will affect State Highway 60 from Motueka to Tākaka. Road users must drive to the conditions and should check weather and road conditions before travelling. Heavy rain can cause slips and localised flooding, and roads may be closed at short notice.
    Metservice Weather Warnings

North Island

  • This coming week sees monthly State Highway tunnel maintenance carried out in Wellington city on Monday and Tuesday nights. Contractors will be working in The Terrace and Mt Victoria Tunnels. Full closures are required, and drivers will have to take alternative routes while this work is underway.
  • There will be night-time lane closures on State Highway 59, Porirua, on Tuesday and Wednesday night for resurfacing works. Local detours will be available, but regular highway users plan their travel to avoid delays.
  • The latest dates for planned night works and road closures for State Highway 2, Remutaka Hill, have been announced.
    Latest dates for State Highway 2 Remutaka Hill planned maintenance closures

South Island

The details below outline the main planned state highway roadworks occurring in the greater Wellington region and the top of the South Island over the coming week (from Saturday, 8 July). Further details about regional state highway conditions and roadworks are also published on our website:

NOTE: Roadworks are dependent on weather and other factors. Bad weather can see work postponed to the next suitable night in the works programme.

Wellington, Porirua, Kāpiti, Hutt

State Highway 1

SH1 Wellington, Monthly Tunnel Maintenance Closures, 9 pm-5.30 am

  • Terrace Tunnel – Monday night
  • Mt Victoria Tunnel – Tuesday night
  • Please use alternative routes

SH1 Ngauranga Flyover northbound ROAD CLOSED

  • Wednesday, 9 pm-4.30 am
  • Resurfacing works
  • Use Hutt Road or follow detour signs

SH1 Ngauranga Flyover, northbound

  • Sunday to Tuesday, 7 pm-5.30 am
  • Northbound one lane closed for asphalt resurfacing

SH1 Tawa interchange to Glenside interchange

  • Sunday, 7 pm-5.30 am
  • Southbound one lane closed for asphalt resurfacing

SH1 North of Ōtaki, near Pukehou Bridge

  • Sunday and Wednesday nights, 7 pm-5:30 am
  • Stop/go traffic control for turn-around bay construction

State Highway 59

SH59 Porirua, ROAD CLOSED southbound between Titahi Bay offramp and Mungavin interchange

  • Tuesday, 9 pm-4.30 am
  • Resurfacing works
  • Detour via local roads via Titahi Bay offramp to Mungavin interchange

SH59 Porirua, ROAD CLOSED southbound between Mungavin and Kenepuru interchanges

  • Wednesday, 9 pm-4.30 am
  • Resurfacing works
  • Detour via Mungavin interchange, local roads to Transmission Gully Motorway

SH59 North of Paekākārikinear Transmission Gully interchange

  • Sunday to Wednesday, 7 pm-5.00 am
  • Stop/go traffic control for water main works

State Highway 58

SH58 Haywards Hill Road

  • Sunday to Thursday, 7 pm–6 am
  • Stop/go traffic control for safety project

SH 58 Paremata-Haywards, westbound Road CLOSED, between Pāuatahanui roundabout to SH58/SH1 interchange

  • Sunday and Monday nights, 9 pm–4.30 am
  • Westbound lanes CLOSED for road reconstruction works
  • Local road detour signposted

SH 58 Paremata-Haywards westbound, between Pāuatahanui roundabout to SH58/SH1 interchange

  • Tuesday and Wednesday nights, 6 pm–5.30 am
  • Stop/go traffic control for road reconstruction works

State Highway 2

SH2 Upper Hutt, near Whakatiki Street intersection

  • Tuesday and Wednesday nights, 7 pm-5.30 am
  • Stop/go traffic control for median barrier upgrades

SH2 Upper Hutt, between Whakatiki Street to Gibbons Street

  • Sunday and Monday nights, 7 pm-5.30 am
  • Stop/go traffic control for median barrier upgrades

SH2 Upper Hutt, near Gibbons Street intersection

  • Monday and Tuesday nights, 7 pm-5.30 am
  • Stop/go traffic control for median barrier upgrades

SH2 Upper Hutt, Totara Park intersection

  • Wednesday, 7 pm-5.30 am
  • Stop/go traffic control for barrier upgrade

Wairarapa state highways

State Highway 2

SH2 Between Carterton and Masterton

SH2 South of Featherston, near Otauira Reserve

  • Tuesday and Wednesday during the day, 8 am-4 pm
  • Stop/go traffic control for roadside levelling

SH2 North of Greytown, near Ahikouka Road

  • Sunday and Monday nights, 7 pm-5.30 am
  • Stop/go traffic control for drainage works

SH2 Mt Bruce, North of Bruce Road

  • Monday, 8 am-4 pm
  • Stop/go traffic control for culvert clearing

Marlborough state highways

State Highway 1

SH1 Tuamarina

  • Monday to Thursday
  • Pre-seal Works
  • Stop/Go Traffic Management

SH1 Weld Pass, Blenheim

  • Wednesday
  • Pre-seal Works
  • Stop/Go Traffic Management

State Highway 6

SH6 Nelson Street, Blenheim

  • Ongoing until July
  • Watermain works
  • Marlborough District Council project

SH6 between St Leonards and Jacksons Roads

  • Monday and Tuesday
  • Drainage works
  • Stop/Go Traffic Management

SH6 Kaituna

  • Wednesday and Thursday
  • Drainage works
  • Stop/Go Traffic Management

Nelson/Tasman state highways

State Highway 6

SH6 Rai Saddle to Hira

  • 15 May to 17 July, 7 am – 6 pm daily
  • Scour protection below slip sites and general maintenance Expect 10-minute delays
  • Stop/Go traffic control and 30 km/h temporary speed restrictions in various locations

SH6 Tahunanui Drive, Bisley Avenue to Green Street

  • Monday – Wednesday, 7 pm-6 am
  • Street light replacement installation between Rui Street and Green Street
  • Traffic Management: stop/go, temporary speed limit of 30 km/h

SH6 Dellow’s Bluff, Murchison

  • 30 km/h speed restrictions. Road is open to two lanes
  • Rockfall area

SH6 south of Three Brothers’ Corner

  • Tuesday, 8 pm – 5 am
  • Road surface testing – Between Three Brothers’ Corner and Farmlands Co-Operative outlet
  • Traffic management: stop/go with 30 km/h speed restrictions. 
  • No unattended speed restrictions during the day

State Highway 60

SH60 Motueka, High Street

    • Wednesday, 8 pm – 5 am
    • Road surface testing – between Tudor Street and Woodlands Avenue
    • Traffic management: stop/go with 30 km/h speed restrictions. 
    • No unattended speed restrictions during the day

SH60 Bird’s Hill, Golden Bay

  • Road is open to two lanes, 50km speed restriction.
  • Road underslip work

Update 7 July 1:35pm:

Tomorrow’s closure (8 July) of SH1 Desert Road between Rangipo and Waiouru is not going ahead as planned.

Stop/Go is underway here today until 5pm for the removal of debris off the highway.

A new date for the closure for a truck recovery is to be advised.

SH1 between Taupō and Turangi will close on Monday 10 July for log retrieval.

The highway will be closed from 8am to 4pm between Taupō airport and Turangi with traffic diverted via SH41 and SH32.

The log retrieval is required due to a logging truck and trailer that went over the edge at Te Pōporo (Bulli Point) beside Lake Taupō on 5 July.

While the truck and trailer was successfully retrieved yesterday, Waka Kotahi contractors require an additional day to remove the remaining logs.

This updates the advisory below. 


6 July 2023 4:36pm

State Highway 1 between Taupō and Turangi will reopen at 7pm tonight following the successful retrieval of a truck and trailer that went over the edge at Te Pōporo (Bulli Point) beside Lake Taupō yesterday afternoon.

The highway has been closed since 7am this morning with traffic diverted via State Highway 41 (SH41) and State Highway 32 (SH32).

Two cranes were required to recover the truck and trailer as well as some of the logs, which were loaded into a waiting logging truck. Unfortunately not all of the logs have been able to be retrieved and a further closure will be required early next week to remove the rest of them. Timing to be confirmed.

Geotech assessed the site and found cosmetic but no structural damage to the retaining wall.

SH1 Desert Road truck crash

Earlier today a produce truck crashed on the Desert Road, ending up in the ditch at Mangamate. Waka Kotahi contractors will close one lane on SH1 tomorrow to remove debris from the road. Road users should expect delays.

Saturday 8 July there will be a full closure between Rangipo and Waiouru from 8am till 4pm for the truck recovery.

Detour for northbound traffic is SH49 via Ohakune, SH4 and SH47 past Whakapapa and then using SH46 to re-join SH1 at Rangipo. The detour for southbound traffic follows the same route but in the opposite direction.

Waka Kotahi thanks road users for their patience.

 

Please note this Traffic Bulletin is updated every Friday.

Daily updated closure information 

Unless otherwise stated, closures start at 9pm and finish at 5am.

NORTHERN MOTORWAY (SH1)

  • Southbound lanes between Orewa off-ramp and Silverdale on-ramp, 9-10 July (approx. 10:00pm to 5:00am)
  • Orewa southbound on-ramp, 9-10 July
  • Millwater southbound on-ramp, 9-10 July
  • Oteha Valley Road southbound on-ramp, 11 July
  • Onewa Road northbound off-ramp, 11 July (approx. 9:30pm to 5:00am)
  • Onewa Road northbound on-ramp, 12 July
  • Onewa Road southbound on-ramp, 12 July
  • Stafford Road northbound off-ramp, 11 July (approx. 9:30pm to 5:00am)
  • Shelly Beach Road southbound off-ramp, 12 July (approx. 10:30pm to 5:00am)
  • Curran Street northbound on-ramp, 11 July

CENTRAL MOTORWAY JUNCTION (CMJ)

  • Fanshawe Street southbound off-ramp, 12 July (approx. 10:30pm to 5:00am)
  • Southbound lanes between Fanshawe Street off-ramp and Greenlane on-ramp, 10-11 July (approx. 10:00pm to 5:00am)
  • SH1 southbound to SH16 westbound link, 10-11 July (approx. 10:00pm to 5:00am)
  • SH1 southbound to SH16 eastbound (Port) link, 10-11 July (approx. 10:00pm to 5:00am)
  • Hobson Street southbound on-ramp, 10-11 July
  • SH16 eastbound to SH1 southbound link, 10-11 July (approx. 10:00pm to 5:00am)
  • Symonds Street southbound on-ramp, 10-11 July
  • Westbound lanes between Stanley Street off-ramp and Wellesley Street East on-ramp, 10-11 July (approx. 10:00pm to 5:00am)
  • SH16 (Port) westbound to SH1 southbound link, 10-11 July (approx. 10:00pm to 5:00am)
  • Grafton Road southbound on-ramp, 10-11 July

SOUTHERN MOTORWAY (SH1)

  • Khyber Pass Road southbound on-ramp, 10-11 July
  • St Marks Road southbound on-ramp, 10-11 July
  • Southbound lanes between Greenlane off-ramp and Mt Wellington Highway on-ramp, 9 July (approx. 11:00pm to 5:00am)
  • Greenlane southbound on-ramp, 9 July (approx. 10:00pm to 5:00am)
  • Tecoma Street southbound on-ramp, 9 July (approx. 10:00pm to 5:00am)
  • Ellerslie-Panmure Highway southbound on-ramp, 9 July (approx. 10:00pm to 5:00am)
  • Northbound lanes between Papakura off-ramp and Takanini on-ramp, 10 July
  • Papakura (Diamond) northbound on-ramp, 10 July
  • Papakura (Loop) northbound on-ramp, 10 July
  • Papakura southbound off-ramp, 12 July
  • Papakura southbound on-ramp, 7-15 July (24/7)
  • Southbound lanes between Mercer off-ramp and Mercer on-ramp, 9-10 July (approx. 11:00pm to 5:00am)
  • Northbound lanes between Mercer off-ramp and Mercer on-ramp, 9-10 July (approx. 11:00pm to 5:00am)

NORTHWESTERN MOTORWAY (SH16)

  • Lincoln Road southbound off-ramp, 9-11 July (approx. 8:00pm to 5:00am)
  • Lincoln Road northbound on-ramp, 11-12 July
  • Northbound lanes between Great North Road off-ramp and Patiki Road on-ramp, 9 July (approx. 10:00pm to 5:00am)
  • Rosebank Road northbound off-ramp, 9 July (approx. 10:00pm to 5:00am)
  • Great North Road northbound on-ramp, 9 July
  • SH16 eastbound to SH20 southbound link (Waterview Southbound Tunnel closed), 10 July
  • Great North Road eastbound off-ramp (Waterview Southbound Tunnel closed), 10 July
  • SH16 westbound to SH20 southbound link (Waterview Southbound Tunnel closed), 10 July
  • Great North Road westbound off-ramp, 11-12 July (approx. 9:00pm to 6:00am)

UPPER HARBOUR MOTORWAY (SH18)

  • Tauhinu Road westbound on-ramp, 10 July
  • Squadron Drive westbound off-ramp, 10 July

SOUTHWESTERN MOTORWAY (SH20)

  • Southbound lanes between Massey Road off-ramp and Puhinui Road on-ramp, 10 July (approx. 10:00pm to 5:00am)
  • Massey Road southbound on-ramp, 10 July

GEORGE BOLT MEMORIAL DRIVE (SH20A)

None planned

PUHINUI ROAD (SH20B)

None planned

STATE HIGHWAY 22 (SH22)

None planned

STATE HIGHWAY 2 (SH2)

None planned

 

Please follow the signposted detours. Waka Kotahi thanks you for your co-operation during these essential improvements and maintenance.

Current overnight closure information 

Auckland roads and public transport 

The programme is part of a wider commitment by Waka Kotahi and the Mt Messenger Alliance to tread lightly on the land and involves pest management, restoration and landscape planting, and ecological protection.

Te Ara o Te Ata: Mt Messenger Bypass

The project aims to greatly improve the natural environment in the Mt Messenger area, helping native species to thrive, as well as building a new 6km section of State Highway 3 in north Taranaki.

Since August last year, the Alliance team has trapped 449 rats in the project’s pest management area and wider Parininihi block. 171 possums have also been removed, along with 188 goats, 11 wild cats, and 29 stoats and weasels.

Additionally, the team has established more than 190km of a planned 250km of pest management tracks, and installed bait stations in forest around the new section of SH3.

Alliance lead ecologist Roger MacGibbon says predators such as rats, stoats and possums have, over decades, seriously impaired the mature native forest surrounding the route of the future 6km bypass, and the wildlife that lives in that habitat.

“Our pest management programme will support the forest’s recovery from this damage. We’re committed to leaving the area in a better state than we found it.

“Along with a major programme of restoration planting, our enduring pest management programme will help our iwi partner Ngāti Tama protect the whenua for generations to come.”

Part of the programme includes an upcoming aerial bait application that will make further inroads into the pest population. This joint Waka Kotahi/Department of Conservation operation will target rats and possums that can’t be reached by ground-based pest management work.

From this month, helicopters with calibrated buckets will distribute biodegradable 1080 bait along pre-determined and monitored flight paths over an area of 5,000ha. A ‘pre-feed’ of non-toxic bait will be sown first, to prime the rodents and possums, ahead of the 1080 bait which will be distributed at least five days later. Each operation will take a day to complete.

Aerial application of cereal pellets containing 1080 is the most effective control method over large areas. It is the only viable method in large, remote, forest-covered and rugged areas. Ground-based trapping and bait stations are effective in smaller more accessible areas, however the number of possum/rodents and stoats can sometimes overwhelm trapping networks. In these areas aerial 1080 can be used to supplement the existing ground-based work.

1080 dilutes rapidly to harmless levels in waterways – it is almost always undetectable after 24 hours. Because it is a natural compound (found in Australian and South African plants), 1080 is degraded by microorganisms in the soil and does not build up in insects, fish or plants.

More information on biodegradable 1080 is available on the DOC website.

1080: New Zealand pest control methods

Road crews will inspect the road surface and take samples ahead of future road reconstruction work as part of regular state highway maintenance.

The work will be done on Wednesday, 12 July, between 8 pm and 5 am. The location will be High Street, between Tudor Street and Woodlands Avenue.

To give our contractors a safe space to do their work, the road will be reduced to one lane with 30 km/hr temporary speed restrictions and Stop/Go traffic lights in place.

The work has been deliberately timed to happen at night when traffic volumes are lower, and every effort is being made to minimise the impact on residents and road users. However, some short travel delays can be expected.

Waka Kotahi appreciates road works can be frustrating. However, this work is essential to the state highway maintenance programme. Knowing the state of the road ahead of reconstruction allows our contractors to better plan jobs and projects.

As we head into the second weekend of school holidays, more people are likely to be on the road so it’s important to drive to the conditions.

This means slowing down, increasing following distances, switching headlights on, and watching for flooding and other debris on the road.

While Waka Kotahi contractors have comprehensive winter maintenance plans in place, they rely upon road users driving to the conditions. Slow down if the road is wet and avoid sudden braking.

Our contractors will have teams onsite monitoring conditions and ready to respond if needed.

Bad weather can see state highways closed at short notice. Drivers are encouraged to check the very latest weather conditions before they travel.

People should continue to keep an eye on the Waka Kotahi Journey Planner website for the latest information on road conditions.

Journey Planner


Update 9:45 am:

The crash scene has been cleared and the highway is now fully open in both directions. Some travel delays are likely as queued traffic clears.

Waka Kotahi wants to thank drivers for their patience and cooperation during this morning’s closure, while emergency services and contractors attended this incident.


Update 9.10 am:

State Highway 60, Mapua, now partially open following crash

One lane of the highway between Mapua Drive and Aporo Road has been reopened to traffic heading towards Motueka. 

The other lane remains closed for traffic heading towards Mapua. Drivers heading in this direction must use local road detours.

Contractors and emergency services remain at the scene and efforts to fully reopen the road are continuing.


8:18am

Due to a crash, State Highway 60 is closed this morning between Aporo Road and Mapua Drive.

The incident, involving multiple vehicles, was reported around 8 am this morning. 

Driver travelling on State Highway 60 between Tasman and Mapua, should avoid the area, delay their journey or consider an alternate route. 

Local road detours are available.


District:

Eastern

Police are responding to a serious crash on the Hawke’s Bay Expressway, Waiohiki.

The Serious Crash Unit has been advised.

The road will be closed to allow emergency services to attend.

Motorists are advised to avoid the area.

Further information will be provided when available.

ENDS

Issued by Police Media Centre